  List of Under Construction
List of under construction

Item
Project
Project Scale
Owner
 
Work Period
Site
Standard of Scaffolding
1
Scaffolding erectionand dismentling of FPSO in MODEC Australia  project construction
4200 Tons
MODEC
in progress
Qingdao Yard of CNOOC
AS
2
Scaffolding erection and dismentling of LD15-1 module  in Ledong  project construction
1800 Tons
CNOOC
in progress
Qingdao Yard of CNOOC
AS
3
Scaffolding erection and dismentling of JZ25-1S CEP  module  in Jinzhou  project construction
4400 Tons
CNOOC
in progress
Qingdao Yard of CNOOC
AS
4
Scaffolding erection and dismentling of JZ25-1S WHPA  module  in Jinzhou  project construction
3000 Tons
CNOOC
in progress
Qingdao Yard of CNOOC
AS
5
Scaffolding erection and dismentling of the 800 tons gantry crane  project construction
4500 Tons
CNOOC
in progress
Qingdao Yard of CNOOC
AS
6
Scaffolding erection and dismentling of LD27-2/32-2 WHPA modules in luda project construction
3100 Tons
CNOOC
in progress
Qingdao Yard of CNOOC
AS
7
Scaffolding erection and dismentling of 250FT self-elevate 1# drilling ship project construction
4000 Tons
CNOOC
in progress
Qingdao Yard of CNOOC
AS
8
Scaffolding erection and dismentling of 250FT self-elevate 2# drilling ship project construction
4000 Tons
CNOOC
in progress
Qingdao Yard of CNOOC
AS
9
Scaffolding erection and dismentling of 250FT self-elevate 3# drilling ship project construction
4000 Tons
CNOOC
in progress
Qingdao Yard of CNOOC
AS
10
Scaffolding erection and dismentling of 250FT self-elevate 4# drilling ship project construction
4000 Tons
CNOOC
in progress
Qingdao Yard of CNOOC
AS
11
Blasting and painting, scaffold erection and dismantlement of Halfden Phase ¢ôJacket in MOG project construction
2500 Tons
Maersk & SMOE
in progress
Shenzhen Chiwan Yard
GB
12
Blasting and painting, scaffold erection and dismantlement in C1117 SINO BARGE LOADER project construction
1500Tons
SANDVIK MC Material Handing GmbH &Co KG
in progress
Shenzhen Chiwan Yard
GB
13
Blasting and painting, scaffold erection and dismantlement of jacket and module Reindeer Wellhead Platform Project construction
3395 Tons
APACHE ENERGY LIMITED
in progress
Shenzhen Chiwan Yard
GB
 
Copyright © Shenzhen Yuanming Industrial Co.,Ltd   Address:Chiwan Building Chiwan Road Shekou Shenzhen Guangdong P.R. China